A 1,500 kW IT hall at a design PUE of 1.3 needs 1,950 kW of facility load, or 2,437 kVA at 0.8 power factor. In Indonesia that load is carried on 50 Hz sets at 380/220 V, 1500 rpm, usually inside containers and usually in N+1. Three 1,600 kVA sets give 2,432 kW with one set out after a 45 C derating, which is 80% of the load. The frequency, the voltage, the container cooling and the biodiesel blend are the four items that separate an Indonesian build from a Philippine one.
Why containerised, and why 50 Hz changes the build
Indonesian data centres are built on islands with different logistics: Batam and Jakarta are port sites, Surabaya and Morowali are industrial sites, and the further the project sits from a container terminal, the more the enclosure decides the schedule. A containerised set arrives as a tested package with its own canopy, tank, control panel and cable entry, and it can be set on a plinth and connected in days rather than weeks.
None of that changes the electrical fact: Indonesia is a 50 Hz network. A set built for the Philippines cannot be re-rated by changing a setting, and a container ordered for a 60 Hz project will not connect to a 50 Hz bus.
| Item | Indonesia (50 Hz) | Philippines (60 Hz) |
|---|---|---|
| Engine speed | 1500 rpm | 1800 rpm |
| LV voltage | 380/220 V | 440/254 V |
| Current at 1,600 kVA | 2,431 A | 2,100 A |
| Alternator | 4-pole, 50 Hz winding | 4-pole, 60 Hz winding |
| Cooling and fan | Sized for 50 Hz speed and ambient | Sized for 60 Hz speed and ambient |
| Typical MV distribution | 20 kV | 13.8 kV or 34.5 kV |
The current difference matters more than it looks. At 380 V, a 1,600 kVA set delivers 2,431 A, so the busbar, the breaker frame and the cable are all larger than the 440 V equivalent. A plant with four sets in parallel at 380 V is a very large copper project; above roughly 2,000 kVA per set, many Indonesian data centres generate at 6.6 kV or 11 kV and step down, which moves the paralleling bus to a manageable current. That is a design decision to make before the containers are ordered, because it changes the alternator winding and the switchgear, not just the transformer.
The full set of differences between the two grids is in 50 Hz vs 60 Hz generators. The rest of this article assumes a 50 Hz build at 380/220 V, with the medium-voltage option noted where it changes the answer.
Step 1: size from the IT load, not from the container
The sizing method is the same one used for any data centre: IT load, PUE, power factor, redundancy. What changes in Indonesia is the PUE assumption and the ambient the container actually sees.
| Step | Value | Note |
|---|---|---|
| IT load | 1,500 kW | The critical load the hall is designed to carry |
| Design PUE | 1.30 | Chilled water plant, pumps, UPS losses, tropical humidity |
| Facility load | 1,950 kW | 1,500 x 1.30 |
| Apparent power at 0.8 PF | 2,437 kVA | 1,950 / 0.8 |
| N+1 with 1,600 kVA sets | 3 sets | One out: 2,432 kW after 5% derating |
| Loading with one set out | 80% | 1,950 / 2,432 |
The 1,600 kVA choice is not arbitrary. Two 2,000 kVA sets give 3,200 kW with one out before derating, which fails: 1,950 kW needs 2,437 kVA, and one 2,000 kVA set leaves 1,520 kW after derating. Three 1,250 kVA sets also fail: 1,250 kVA is 1,000 kW, or 950 kW after derating, and two remaining sets give 1,900 kW against a 1,950 kW load. The three 1,600 kVA arrangement is the smallest standard combination that passes with margin.
Two cautions on the PUE. A design PUE of 1.3 assumes a chilled water plant with good part-load control; a tropical hall with direct expansion units and high humidity can design closer to 1.4, which moves the facility load to 2,100 kW and the set count. And the generator carries the mechanical plant at the moment of transfer, including chiller restart, so the design maximum is the number to use, not the annual average. The method is set out in data centre generator sizing, and the N+1 arithmetic is in generator paralleling and N+1.
Step 2: what the container has to include
A container is not a shed around a generator. It is a package that has to manage airflow, noise, fire separation, fuel and access at the same time, and the specification decides which of those the supplier actually delivers.
| Item | What to specify | Why it matters on an Indonesian site |
|---|---|---|
| Enclosure | 40 ft high-cube, 12.19 x 2.44 x 2.89 m, walk-in access where the layout allows | Road transport, container ship and crane capacity all follow this size |
| Weight | Typical 12-18 t for the complete package; confirm the lifting points and spreader beam | Site cranes and barge handling are sized on the real figure |
| Integral tank | 8-24 hours of fuel in the base tank, with a bund and a fill point outside the door | An integral tank keeps the first day of operation independent of a bulk tank |
| Louvres | Separate intake and discharge, rain hoods, insect screens, sand and dust filters | Driving rain and dust are the two things that stop a container plant |
| Acoustic lining | Declared dB(A) at the boundary, not only at 1 m from the container | Data centres near residential areas are judged at the fence line |
| Fire separation | Steel bulkhead between the set compartment and the tank or control compartment | A fuel fire next to the control panel takes the whole plant out |
| Corrosion protection | Coating system for the site’s corrosion category, with touch-up kit | Batam and Jakarta coastal air attacks terminals and enclosure steel |
| Cable entry | Gland plate with removable sections, sized for the 2,431 A LV cable or the MV cable | Retrofitting a cable entry on site is a cutting job with the set inside |
| Controls | Paralleling controller, ATS interface, remote monitoring and a defined failure mode | The container is unmanned most of the time; the alarm has to reach someone |
Two items on that list are usually under-specified. The first is the tank: a container with an integral 1,000 L tank gives about two hours at full load on a 1,600 kVA set, which is not a data centre autonomy figure. The integral tank is a day tank; the bulk tank is a separate civil and mechanical project. The second is cable entry: a 1,600 kVA set at 380 V needs 2,431 A, and the cable or busbar for that current does not fit through a gland plate designed for a 630 A set.
Step 3: cooling, humidity and salt
A container in Jakarta or Batam sits in 32-35 C air with humidity near saturation for much of the year, and the inside of the container is hotter than the outside. The radiator discharges into the same enclosure that houses the alternator, so the design has to keep the hot air from coming back into the intake.
Three rules prevent most container cooling failures:
- Do not face the discharge into the next container’s intake. A row of containers with louvres facing each other creates a loop: one set’s exhaust heats the next set’s cooling air. Lay the containers out with a clear discharge path, or use a ducted discharge.
- Keep the intake and discharge on different faces. If both are on the same side, the wind decides whether the set cools or overheats. Rain hoods and a separation between the two openings are part of the enclosure, not an accessory.
- Specify the ambient the set is rated for. A set rated at 40 C and installed where the container interior reaches 48 C loses more than the 5% planning figure used in this article. Ask for the derating curve at the actual container ambient, and if the supplier cannot provide it, change the supplier.
Humidity and salt need their own measures. Anti-condensation heaters on the alternator and the control panel keep moisture off the windings when the set is idle, which is most of the time. The alternator space heater is not optional in this climate; a set that sits cold for a month in 90% humidity will fail an insulation test before it ever carries load. On the coast, wash the radiator and the enclosure after the dry season, and check terminals for corrosion at every service.
Step 4: fuel, including the biodiesel question
At 0.24 L/kWh, 1,950 kW burns 468 L/h. That number sets the tank, the refuelling contract and the road access.
| Autonomy | Volume | What it implies |
|---|---|---|
| 8 hours | 3,744 L | Integral tank at the upper limit for a 40 ft container |
| 24 hours | 11,232 L | Bulk tank, bund and a refuelling route for a tanker |
| 48 hours | 22,464 L | Two bulk tanks or one large tank with a transfer pump |
| 72 hours | 33,696 L | Fuel farm with fire separation and routine testing |
Indonesia adds a fuel-quality variable that the Philippines does not: the diesel supplied locally commonly contains a biodiesel blend, and the blend ratio has moved upward over time. Biodiesel absorbs water more readily than mineral diesel and supports microbial growth, so the storage life is shorter and the filter sees contamination sooner. Confirm the current blend with the fuel supplier, shorten the test interval, and plan for polishing on a site that stores more than a few days of fuel. Do not assume that a fuel specification written for another country applies.
The fuel path also has to match the redundancy. Three sets fed from one bulk tank through one isolation valve are N+1 on the drawing and N on the day the valve fails. Give each container its own draw-off and isolation, or arrange the manifold so one failure does not stop the plant.
Step 5: 380 V or medium voltage
At 380 V, each 1,600 kVA set delivers 2,431 A, and a three-set parallel bus carries 7,293 A. That is a large busbar and a large amount of copper, and the short-circuit level at the paralleling panel becomes a significant design input. Many Indonesian data centres above a few megawatts generate at 6.6 kV or 11 kV instead: at 11 kV, the same 1,600 kVA set delivers 84 A, and the paralleling switchgear becomes a normal medium-voltage project.
The choice is not only electrical. Medium-voltage generation moves the step-up transformer, the protection and the operating competency requirements into the scope, and it changes who can work on the plant. Low-voltage generation is simpler to operate and easier to service locally, but it stops being practical when the bus current and the cable count grow beyond what the switchgear room can hold. Make the decision with the single-line diagram in front of you, before the alternator winding and the container cable entry are fixed.
Step 6: factory and site tests
A container is tested twice: once at the factory, where the load bank and the instruments are good, and once on site, where the fuel, the earthing and the real load are. Skipping either one moves the discovery to the first outage.
| Stage | Test | Pass criterion |
|---|---|---|
| FAT | Load test at 25, 50, 75 and 100% for 2-4 hours at rated load | Stable voltage and frequency; coolant and exhaust temperatures within the datasheet |
| FAT | Fuel consumption at 75% and 100% | Within the declared curve; the number goes into the fuel plan |
| FAT | Protection trip tests: overcurrent, earth fault, reverse power, over/under frequency and voltage | Correct relay trips the correct breaker |
| FAT | Paralleling and load sharing, if a factory bus is available | Each set within about 5% of its share at 50% and 100% load |
| FAT | Container inspection: louvres, fire bulkhead, cable entry, lifting points, tank bund | Matches the general arrangement drawing |
| SAT | Foundation, anchorage, earthing and neutral arrangement | Resistance values recorded; single neutral-earth bond confirmed |
| SAT | Fuel system, transfer pump, bund and fill point | No leak; the tanker can reach the fill point |
| SAT | Load bank 4 hours at 80-100%, then a 24-hour trial on site load where available | No derating surprise at the real container ambient |
| SAT | ATS and paralleling sequence, including loss of one set | Remaining sets stay at or below 90% of derated capacity |
| SAT | Alarms and remote monitoring | Alarm reaches the monitoring desk, not only the local panel |
The 24-hour site trial is worth the fuel it burns. It is the only test that exposes a container whose louvres recirculate hot air, a fuel system that draws air, or a radiator that was sized for a 40 C day in a laboratory rather than a 35 C afternoon in Batam with the sun on the roof. A four-hour load bank in the factory will not show any of those.
Limits of this guide
- PUE is an assumption. 1.3 is a design figure for a chilled-water hall in a tropical climate; the measured first-year figure is usually higher, and the load list should be checked against it.
- The derating is a planning figure. Five percent at 45 C is used consistently across this site; a container’s internal ambient can be higher, and the datasheet curve decides.
- Fuel burn is a planning figure. 0.24 L/kWh is an estimate near rated output; part-load curves are higher per kWh.
- The biodiesel blend changes. Confirm the current ratio with the fuel supplier; storage life and test intervals follow the blend, not a fixed rule.
- Container dimensions and weights are typical. A 40 ft high-cube package with a larger tank, a different alternator or a medium-voltage switchgear compartment will differ; use the general arrangement drawing.
- Local permits and fire requirements are outside this article. Fuel storage, fire separation and building approval depend on the site’s authority; confirm before the tank and container layout are fixed.
- No price is quoted here. The container, the tank, the medium-voltage option and the paralleling scope move the quotation more than the kVA rating does.
Questions
Is Indonesia 50 Hz or 60 Hz?
Indonesia is a 50 Hz network at 380/220 V, so the engine runs at 1500 rpm and the alternator is wound for 50 Hz. The Philippines is 60 Hz at 440/254 V and 1800 rpm. A set built for one grid cannot be re-rated for the other by changing a setting; the winding, the speed and the cooling are different. The comparison is in 50 Hz vs 60 Hz generators.
How many containerised sets does a 1,500 kW IT hall need?
At a design PUE of 1.3, 1,500 kW of IT load becomes 1,950 kW of facility load, or 2,437 kVA at 0.8 PF. Three 1,600 kVA sets give 2,432 kW with one set out after a 45 C derating, which is 80% loaded. Two 2,000 kVA sets fail because one set leaves 1,520 kW, and three 1,250 kVA sets fail because two remaining sets give 1,900 kW against 1,950 kW.
Why use a container instead of a plant room?
Speed and logistics. A container arrives tested, with its canopy, tank, controls and cable entry, and it can be set on a plinth and connected in days. It also keeps the noise and the fire separation in one package and makes it possible to ship a 1,600 kVA set to an island site as a standard container. A plant room is cheaper per square metre when the building already exists and the site has space, but it moves the enclosure, the tank and the acoustic work into the construction programme.
How much fuel does a 1,950 kW load need?
At 0.24 L/kWh, about 468 L/h. Eight hours is 3,744 L, which is at the upper limit of an integral container tank; 24 hours is 11,232 L and 48 hours is 22,464 L, both bulk-tank projects. A container’s integral tank is a day tank, not an autonomy plan, and the bulk tank needs bunding, fire separation and truck access.
Can I use a Philippine 60 Hz set in Indonesia?
No. The engine speed, the alternator winding, the voltage and the cooling are all declared for one frequency. A 60 Hz set will not hold 50 Hz, and re-rating it is a rebuild, not a settings change. Order the set for the grid it will run on, and state the voltage and frequency in the enquiry.
Does biodiesel in Indonesian diesel change the fuel plan?
Yes. A biodiesel blend absorbs water more readily and supports microbial growth, so storage life is shorter and filters see contamination sooner. Confirm the current blend with the supplier, test more often than the annual interval used for mineral diesel, and plan polishing for a site that stores more than a few days of fuel. The engine’s fuel system also has to be declared for the blend by the manufacturer.
Send the IT load, the PUE and the site
IT load in kW, design PUE, redundancy, the site (Jakarta, Batam, Surabaya or a remote industrial site), the fuel hours and whether you want low-voltage or medium-voltage generation. The reply sets out the set count, the derated capacity with one set out, the container scope and the fuel storage that goes with it.
Written and maintained by the kvagenset sales engineering desk. Ratings are 50 Hz, 380/220 V, 0.8 power factor; the 45 C derating, 0.24 L/kWh fuel figure and 1.3 PUE are stated planning assumptions, not datasheet guarantees. Reviewed 31 October 2026. The data centre application is described on the data centre generator page, and the 2,000 kVA frame on the 2000 kVA generator page.