Application
Diesel Generators for Telecom Sites
A telecom site is judged by one number: minutes of downtime. A cell site on a weak feeder, a transmission hub that carries the traffic of a whole province and an exchange with a data hall all need the same thing – a set that starts on the first attempt, runs unattended, and reports what it did. The machine is usually small; the reliability around it is not.
Cell sites in the Philippines are normally quoted between 20 kVA and 100 kVA in a lockable canopy, on prime power duty where the grid is unreliable. Exchanges, transmission hubs and data halls are quoted between 200 kVA and 1000 kVA on standby duty, in an N+1 group, with the DC power plant as the first load.
Requirements
What a telecom specification has to state
| Item | Typical requirement | Why it changes the set |
|---|---|---|
| Site class | Macro cell site, transmission hub, exchange or data hall | Fixes the rating, the duty and how much redundancy is bought |
| Load to carry | DC rectifiers and battery charging, air conditioning, lighting, security and monitoring | The rectifier bank is a steady load that runs at close to full output for hours |
| Duty | Prime power at off-grid and weak-grid sites; standby at exchanges | A prime-rated set is built to run thousands of hours a year; a standby set is not |
| Autonomy | 8-24 h at a cell site, 24 h or more at an exchange | Decides the base tank, the bulk tank and the refuelling schedule |
| Starting | Automatic on mains failure, and remote start on command | Drives the control panel, the transfer switch and the starting battery |
| Telemetry | Alarms to the network operations centre over the site transmission link | Decides whether the controller needs SNMP, Modbus or volt-free contacts |
| Noise | 60-70 dB(A) at 7 m, tighter at rooftop sites in residential areas | Urban and rooftop sites are the ones that attract complaints and permits |
| Footprint | Pad, plinth or rooftop, sharing the compound with the mast and the equipment cabin | Decides whether the set is canopy-mounted or split with a remote radiator |
| Fuel security | Lockable, bunded tank with a level gauge and a fill point that cannot be siphoned | Fuel theft, not engine failure, is the most common cause of a site going dark |
| Environment | Coastal salt air, humidity above 80%, ambient 35-40 °C, typhoon exposure | Adds anti-condensation heaters, salt-mist treatment and cyclone-rated anchoring |
| Maintenance access | Serviceable by one technician on a scheduled visit, with filters and belts on the shelf | Remote sites are priced on the cost of the visit, not on the cost of the part |
Configurations
Configurations we quote most often
| Rating per set | Typical arrangement | Fits | Range page |
|---|---|---|---|
| 20-60 kVA / 16-48 kW | One set, silent canopy, prime duty, base tank | Off-grid macro cell sites and microwave repeater sites | 100 kVA class |
| 100 kVA / 80 kW | One set, silent canopy, transfer switch, remote start | Weak-grid cell sites and small transmission nodes | 100 kVA |
| 200-300 kVA / 160-240 kW | One set in standby duty, or two in an N+1 group | Transmission hubs and district exchanges | 200 kVA · 300 kVA |
| 500-1000 kVA / 400-800 kW | Two or more sets in parallel, N+1 | Exchanges with data halls and core network equipment | 500 kVA · 1000 kVA |
Reference configuration
A worked cell site example
This is the shape of a quotation for a coastal macro site in the Philippines, not a catalogue entry. The figures below are the ones that changed the build.
| Parameter | Value |
|---|---|
| Rating | 60 kVA prime / 48 kW at 0.8 power factor, 1800 rpm, 60 Hz |
| Voltage | 230 V single phase and 440/254 V three phase available |
| Form | Silent canopy, lockable doors, 65 dB(A) at 7 m, pad mounted on a concrete plinth |
| Autonomy | 12 h at 75% load on a 380 L bunded base tank with a lockable fill point |
| Control | Auto start on mains failure, remote start and stop, volt-free alarm contacts to the site controller |
| Corrosion protection | Salt-mist treated canopy and fasteners, anti-condensation heater on the alternator |
| Anchoring | Cyclone-rated anchor bolts and a canopy rated for the wind zone of the site |
| Testing | Load bank test at 100%, 75% and 50% before dispatch, with the test sheet issued |
Questions
Questions we are asked about telecom sets
Should a cell site generator be prime rated or standby rated?
Prime rated, wherever the grid fails most days. A prime rating allows unlimited hours at a variable load, while a standby rating is meant for the duration of an outage. Sites that run the set as a daily source of power and buy a standby rating are the ones that come back with a failed alternator or a burnt exhaust valve at a few thousand hours.
How much autonomy does a telecom site need?
It follows the refuelling reach. A site that a truck can serve within a day is normally quoted at 12-24 h; a site reached by boat or a rough road is quoted at 48 h or more, or given a bulk tank. The battery bank at the site and the generator autonomy are two separate reserves and should be sized as such.
How do you keep the alarm reporting working when the site is unattended?
The controller sends its alarms over the transmission link the site already has, either through the operator’s own telemetry or as volt-free contacts wired into the site controller. Specify which one you want at the quotation stage: a panel with the wrong interface means the first alarm arrives when a technician drives past, not when the site fails.
What does humidity do to an unattended set?
It condenses on the alternator windings while the set is cold and not running, and insulation resistance falls. An anti-condensation heater with a thermostatic switch is the standard fix, and it is cheap at the factory. Coastal sites also need salt-mist treatment on the canopy, the fasteners and the radiator, or the enclosure is rusting through in three to four years.
Can a small set be paralleled for a bigger site?
Yes, and telecom operators do it where two small sets are easier to truck in than one large one. Paralleling needs the right controllers and the right switchgear, both of which change the cost more than the rating does. On a remote site the practical limit is usually the maintenance team, not the machine.
Related
Related applications and ranges
-
Diesel generators by application
How the requirement changes between data centres, hospitals, hotels, telecom sites and mines.
-
Data centres
N+1 and 2N topologies, load steps and the fuel systems that go with them.
-
Silent sets
Canopy builds for rooftop and residential sites with a noise limit.
-
100 kVA class
80 kW, the common size for a cell site or a small transmission node.
-
Philippines
60 Hz, 220/440 V, Manila and Cebu ports, salt air and typhoon exposure.
-
Request a quote
Send the site class, the load and the autonomy, and we size the set.
Specifying a telecom standby or prime set?
Send the site class, the rectifier and air-conditioning load, the autonomy you need and the interface to your network operations centre.