A mine is a prime-power site, not a standby site: the sets run for most of the year, and the plant is sized from the running load plus the largest motor started across the line, not from a round kVA number. A 1,100 kW Indonesian mine load with a 250 kW ball mill on a direct-on-line start points to 3 × 1,000 kVA prime sets in N+1 – two running near 70% load, one standby – burning about 264 L/h and 6,400 L/day at 50 Hz, 380 V. The steps below show how that answer is reached and where it changes.
Prime power, not standby
A mining plant is the clearest case of prime duty on this site: where there is no grid, the sets are the grid. The load runs 24 hours a day for weeks at a time, and the engines spend most of their life between 60% and 90% of rated output. That is a different machine from a standby set that starts twice a year and runs for a day.
The difference is set out in prime vs standby power: a prime set is rated for continuous variable load with a load factor allowance, while a standby set is rated for the duration of an outage. Specifying a standby-rated set and running it as prime shortens the overhaul interval and burns more fuel per kilowatt-hour than the rating promises. For a mine, write “prime” or “continuous” into the specification first, then choose the kVA.
Why 50 Hz changes the Indonesian build
Indonesia runs 220 V single-phase and 380 V three-phase at 50 Hz, so the same frame turns at 1,500 rpm instead of the Philippine 1,800 rpm at 60 Hz. The alternator is wound for 50 Hz, the engine is governed for 1,500 rpm, and the derating and current figures are read from a 50 Hz datasheet, not a 60 Hz one. The full split is in 50 Hz vs 60 Hz generators.
The practical consequences for a mine are three. First, 50 Hz sets are quoted at 380/220 V, 0.8 power factor, the same convention used in the rest of this site. Second, a 50 Hz motor has a lower synchronous speed, which is easier on the drivetrain but does not remove the starting current – the starting kVA still decides the bus. Third, the enclosure envelope is the same as the 60 Hz version, so transport and footprint do not change.
Step 1: build the load list, then find the largest motor
The plant is sized from the load list with diversity applied, not from a count of motors. A mine list is a few large drives and a long tail of small loads, and the largest motor – not the total – is what forces the set count up. The table below is a representative 1,100 kW plant; treat it as a model, not as a survey of any particular site.
| Load | Running kW | Start method | Start step |
|---|---|---|---|
| Ball mill | 250 | Direct-on-line | about 1,875 kVA (6 × running) |
| Crusher | 160 | Soft starter | about 450 kVA (2.5 ×) |
| Conveyors, six drives | 120 | Direct-on-line, largest single | about 180 kVA |
| Dewatering pumps, three | 150 | Direct-on-line, largest single | about 280 kVA |
| Slurry pump | 110 | Variable speed drive | about 150 kVA |
| Ventilation fans | 90 | Direct-on-line | about 170 kVA |
| Camp, offices, lighting | 120 | Stepped, across the line | small, staggered |
| Workshop and small loads | 100 | Direct-on-line | small, staggered |
| Total, diversity applied | 1,100 | largest step about 1,875 kVA |
The ball mill row is the one that decides the plant. At six times running current its starting step is about 1,875 kVA – bigger in kVA terms than the whole running plant for a few seconds. That is why the answer is a paralleling bus with more than one set, rather than one large set sized to the peak: the bus must carry the running load plus the start step without the voltage dipping far enough to drop contactors. The load-list method is worked through in how to size a diesel generator.
Step 2: prime, continuous or N+1
Three duty names appear on mine specifications, and they are not interchangeable.
| Duty | Load factor | Hours per year | Where it fits on a mine |
|---|---|---|---|
| Standby | 70% of standby rating, intermittent | a few hundred | Camp emergency, ventilation, communications |
| Prime | 70% average of prime rating, variable load | unlimited | Most mine power plants |
| Continuous | 100% of rating, constant load | unlimited | Base-load crushers and mills running flat out |
For 1,100 kW of running load plus a 1,875 kVA start step, two 1,000 kVA prime sets running give 1,600 kW of capacity between them – about 69% load, inside the efficient band – and the bus shares the ball mill transient. The third set is the N+1: it is not a spare sitting in a crate, it is a running asset that lets one engine be serviced while the plant keeps producing. The argument for N+1 over one big set is set out in generator paralleling and N+1.
Step 3: derating for heat, humidity and altitude
Indonesian sites are hot and humid rather than high: most mine and smelter sites sit near sea level with 30-35 °C ambient and high relative humidity, while a few highland sites add altitude. The derating is applied to the engine and alternator before the set is chosen, and it is read from the datasheet, not guessed.
| Condition | Planning allowance | Notes |
|---|---|---|
| Ambient 40 °C | no derate | ISO 8528-1 reference temperature |
| Ambient 45 °C | about 5% off output | verify against the engine datasheet |
| Altitude above 1,000 m | about 3% per 300 m | highland sites only; most Indonesian mines are coastal or lowland |
| High humidity, coastal salt | no direct output derate | changes the enclosure and corrosion specification, not the rating |
The derating is applied before the load is matched, which means a site that needs 1,000 kW at 45 °C is not quoted from the 40 °C datasheet. In practice the 5% allowance at 45 °C moves a 1,000 kVA prime frame down by about 40 kW, and that is enough to change the set count if the margin was already thin.
Step 4: fuel at a remote site
Fuel is the largest operating cost of a mine power plant, and on a remote Indonesian site the constraint is logistics, not price. The burn figures below are the same planning values used across this site: 0.24 L/kWh at 75% load, 0.25 at 50%, 0.30 at 25% and 0.235 at 100%, at 0.8 power factor.
| Frame | kW prime | 25% load | 50% load | 75% load | 100% load |
|---|---|---|---|---|---|
| 800 kVA | 640 | 48 L/h (0.30) | 80 L/h (0.25) | 115 L/h (0.24) | 150 L/h (0.235) |
| 1,000 kVA | 800 | 60 L/h (0.30) | 100 L/h (0.25) | 144 L/h (0.24) | 188 L/h (0.235) |
| 2,000 kVA | 1,600 | 120 L/h (0.30) | 200 L/h (0.25) | 288 L/h (0.24) | 376 L/h (0.235) |
Indonesian diesel is supplied as a biodiesel blend – B30 to B35 depending on the year and the supply contract – and that changes how the fuel is stored. FAME holds water and grows microbes faster than straight diesel, so a remote bulk tank needs a polishing loop, regular water draw-off and a six-month test regime rather than a fill-and-forget schedule. The storage and day-tank logic is set out in fuel consumption and day tanks; the Philippine B2 case there is the same method applied to a different blend.
| Item | Planning figure | Why it is that number |
|---|---|---|
| Plant burn | 264 L/h, about 6,400 L/day | 1,100 kW at 0.24 L/kWh |
| Day tank per set | 1,000 L | about 7 hours at one set’s 75% burn of 144 L/h |
| Bulk tank | 45,000 L | seven days of autonomy, with 110% bunding |
| Polishing | recirculation loop, 24 h | removes water and sediment before the day tanks |
| Testing | monthly draw-off, 6-month lab sample | catches water, microbes and blend degradation |
Step 5: containerised or skid, and how it gets to site
Indonesian mine sites are reached by barge and unsealed road, so the set usually travels as a containerised or skid package rather than a bare frame. The choice is between a 20 ft container that becomes the engine room on arrival, and a skid that has to wait for a building.
| Form | Fits | Limits |
|---|---|---|
| 20 ft containerised | Walk-in service in the wet season, standard lifting, secure transit | Heavier and wider on the final road leg |
| Skid under a roof | Lower first cost where a building already exists | Needs the building before the set is useful |
| Canopy | Camp supply, workshops, small dewatering pumps | Limited for large prime sets and dusty yards |
The containerised path is also how Indonesian data centres are supplied, and the transport, tank and test scope carries over directly – see containerised generators for Indonesia data centres and the containerised sets page.
Step 6: dust, salt and the wet season
Dust is the mine’s own weather. Airborne fines load the air filter and the radiator, and when they get wet they conduct, so the electrical joints in the control panel fail first. The answer is heavy-duty air filtration, a sealed enclosure and a shorter service interval; a filter that lasts 500 hours on a clean site lasts a fraction of that beside a crusher.
Coastal and smelter sites add salt and humidity, which corrode terminals, hinges and the enclosure itself before the engine notices. Specify a corrosion-rated enclosure, sealed connectors and a wet-season service plan. These are the same site-condition rules applied on the diesel generators for mining page.
Step 7: control, synchronising and load management
Two or more sets on one bus need a paralleling controller with load sharing, load-dependent start and stop, and synchronising. Load-dependent start and stop is what keeps the running sets near their efficient band while the plant load swings: instead of running all three sets lightly, the controller starts and stops sets so the ones running sit near 70-85% load.
This is not a luxury. A set run below about 40% load for long periods wets its exhaust and glazes its bores, and its fuel per kilowatt-hour climbs sharply – the 0.30 L/kWh at 25% load in the fuel table is the same engine costing 25% more per delivered kilowatt. The control and protection scope is in generator paralleling and N+1.
A worked Indonesian mine plant
The table below closes the loop on the numbers used above. It is a planning model, not a quotation.
| Item | Value |
|---|---|
| Running load | 1,100 kW, diversity applied |
| Largest start step | about 1,875 kVA (250 kW ball mill, direct-on-line) |
| Sets | 3 × 1,000 kVA prime, 800 kW at 0.8 PF |
| Duty | N+1 – two running at about 69% load, one standby for service |
| Electrical | 380/220 V, 50 Hz, 1,500 rpm, three phase |
| Build | 20 ft containerised, dust filtration, heavy-duty air cleaner |
| Control | Paralleling with load sharing and load-dependent start and stop |
| Fuel | 1,000 L day tank per set, 45,000 L bulk tank, polishing loop; 264 L/h and 6,400 L/day at 75% plant load |
| Derating | 40 °C reference; apply about 5% at 45 °C; no altitude derate at sea level |
The 1,000 kVA frame is the building block here because it is large enough to carry half the plant alone and small enough to be barged and trucked without special permits on most Indonesian routes. The same frame is listed on the 1000 kVA diesel generator page.
What this model does not cover
- Every figure is a planning value at 50 Hz, 380/220 V, 0.8 power factor and a 40 °C reference; the engine and alternator datasheets govern, and the factory test report wins where they differ.
- Fuel burn uses 0.24 L/kWh at 75% load, 0.25 at 50%, 0.30 at 25% and 0.235 at 100% – stated planning assumptions, not guaranteed consumption.
- The Indonesian biodiesel blend is described in general terms; the delivered product certificate and the site fuel specification govern.
- No mine name, location, certification or delivery claim is made. The site is described by its load and its conditions only.
- Nothing here is a quotation. Freight, barge legs, duties, civils and commissioning are separate scopes and are priced separately.
Frequently asked questions
How do you size a generator plant for a mine?
From the running load with diversity applied, plus the largest motor started across the line. A 1,100 kW plant with a 250 kW ball mill on direct-on-line start has a start step of about 1,875 kVA, which is what forces the plant to a paralleling bus and N+1 rather than a single large set. The method is the same one in how to size a diesel generator.
Prime or standby for a mine that runs 24 hours a day?
Prime, or continuous if the load is constant. A prime set is rated for unlimited hours at about 70% average load, while a standby set is rated for the duration of an outage – running a standby set as prime shortens its overhaul interval. Write the duty into the specification before choosing the kVA.
How much fuel does a mine power plant burn?
About 264 L/h and 6,400 L/day for a 1,100 kW plant at 75% load, using the site’s planning figure of 0.24 L/kWh. At 25% load the same energy costs 0.30 L/kWh, so a lightly loaded plant burns more fuel per delivered kilowatt, not less. The frame-by-frame table is in the fuel section above.
What derating applies in Indonesia?
Most Indonesian mines are coastal or lowland, so the main allowance is heat: about 5% off output at 45 °C against the 40 °C reference, with a further allowance of about 3% per 300 m only for highland sites above 1,000 m. High humidity and salt change the enclosure and corrosion specification rather than the rating.
Containerised or skid for a remote site?
Containerised is the default for large prime sets: the container becomes the engine room on arrival, is handled with standard lifting gear, and gives the service team a weatherproof place to work in the wet season. A skid only wins where a building already exists, and a canopy suits camp and support loads.
Can one big set replace three smaller ones?
Not cleanly. One big set still has to absorb the ball mill start step and then runs lightly loaded between starts, which wets the exhaust and raises fuel burn per kilowatt-hour. N+1 also means one set can be serviced without stopping production. The trade-off is worked through in generator paralleling and N+1.
Send the load list, the largest motor and the site
Running load in kW, the largest motor and how it starts, site altitude and ambient, the days of fuel autonomy required, and the delivery point. The reply sets out the set count and rating, the duty, the derating applied, the daily fuel burn and the tank sizes – with every assumption stated, so the numbers can be checked against the datasheet.
Written and maintained by the kvagenset sales engineering desk. Ratings are 50 Hz, 380/220 V, 1,500 rpm and 0.8 power factor for Indonesian projects; fuel burn of 0.24 L/kWh at 75% load, 0.25 at 50%, 0.30 at 25% and 0.235 at 100%, a 40 °C ambient reference with about 5% derating at 45 °C, and about 3% derating per 300 m above 1,000 m altitude are stated planning assumptions, not datasheet values or guarantees. The Indonesian biodiesel blend is described in general terms only and the delivered product certificate governs. Reviewed 4 November 2026. The mining application is summarised on the diesel generators for mining page, and the Indonesian delivery context is set out under diesel generators for Indonesia.