A cold storage facility needs a standby generator sized for the compressor and evaporator fan load, not just the floor area. Size at 125–150% of running kW to cover motor starting, at 0.8 PF and a 40 °C ambient reference (ISO 8528-1). A 200 kVA set at 0.8 PF delivers about 160 kW of standby power.
Why a cold storage needs a standby generator
Cold storage only keeps product safe while the refrigeration system is running. A few hours without power can lift stored food, medicine or frozen goods above the safe holding temperature, and every hour of recovery time adds to the spoilage risk. The generator has to start, accept load, and hold voltage and frequency through the biggest load step on the site: the compressor motors.
A warehouse backup generator is therefore sized around the refrigeration load, not around the warehouse lighting. The correct sizing approach is a load calculation plus a motor-starting allowance, which is why we recommend starting with how to size a diesel generator before choosing a set. The generator also has to match the duty it will actually run, which is covered in prime vs standby power.
Loads to include in the calculation
Add every load that can be energised during a blackout, including loads that only run on transfer. The table below shows a typical split for a refrigerated warehouse at 0.8 PF. These are planning figures; a site survey and motor nameplate data take priority.
| Load | Typical share of connected kW | Notes |
|---|---|---|
| Compressors | 60–70% | Largest starting surge, often 6–8× running current for a few seconds on across-the-line start |
| Evaporator and condenser fans | 15–20% | Run continuously while compressors run |
| Defrost heaters | 10–15% | Cyclic; often staged off during transfer |
| Dock equipment, lighting, controls | 5–10% | Controls and monitoring need a clean, stable supply |
Compressors dominate because they are inductive loads. At 0.8 PF a 200 kVA generator delivers about 160 kW, but the motor-starting kVA can briefly exceed the running kW by a wide margin. The starting allowance, not the running load, often decides the set size.
Sizing method and worked example
Start from the running kW of all refrigeration loads that must restart together, multiply by a starting factor, then divide by 0.8 PF to convert to kVA. The starting factor is lower when compressors use soft starters or staged start, and higher when several motors start together.
| Facility type | Assumed running load | Starting factor | Suggested standby kVA |
|---|---|---|---|
| Small cold room | 15 kW | 1.3 | 25–30 kVA |
| Cold storage warehouse | 80 kW | 1.25 | 150 kVA |
| Distribution centre with blast freezers | 300 kW | 1.35 | 550 kVA |
These are planning assumptions at 40 °C and 0.8 PF, not a substitute for a load study. Larger facilities commonly split the load across two or more sets with staged transfer, so the first motor step stays within the generator voltage-dip limit.
Duty rating: standby, prime or continuous
Standby rating allows limited annual running hours at variable load with no overload. Prime rating allows running as the main power source with a 10% overload for a limited period, and continuous rating is for constant load without the overload allowance. For cold storage in areas with long or frequent outages, a prime-rated set can be the safer choice because the engine is approved for extended running at full design load, while a standby set may need load-bank exercise to stay healthy. Always confirm the duty against the manufacturer datasheet.
Transfer time and cold-chain risk
A generator with an automatic transfer switch (ATS) can typically restore power in roughly 10 seconds after a utility failure, allowing for engine start and transfer. Product temperature rises slowly at first because the building envelope and stored goods provide thermal mass, but the risk is the restart sequence: many compressors restarted together can trip an undersized set. Staging compressor restart, keeping defrost heaters off for the first minutes, and interlocking dock doors all reduce the first step of load.
Fuel autonomy and day tanks
Fuel autonomy is the number of hours the set can run at a given load before refuelling. Using the planning fuel figures for a diesel set at 0.8 PF — 0.235 L/kWh at 100% load, 0.24 L/kWh at 75% and 0.25 L/kWh at 50% — the table below shows typical consumption for common sizes.
| Generator size | Standby kW at 0.8 PF | Consumption at 100% load | Consumption at 75% load | 24 h autonomy at 75% load |
|---|---|---|---|---|
| 100 kVA | 80 kW | 18.8 L/h | 14.4 L/h | 346 L |
| 200 kVA | 160 kW | 37.6 L/h | 28.8 L/h | 691 L |
| 500 kVA | 400 kW | 94.0 L/h | 72.0 L/h | 1,728 L |
Consumption is estimated at 40 °C with the figures above and will vary with load, engine condition and ambient temperature. For day-tank sizing, the engine day tank is normally sized for 8 hours at 100% load. See generator fuel consumption for the full method, and confirm the tank and bulk storage against local fire code.
Temperature derating in the Philippines
Diesel generator output is rated at a reference ambient, usually 40 °C under ISO 8528-1, with a maximum altitude of 1000 m. Hotter or higher sites produce less usable power, so the set must be oversized to compensate.
- 40 °C ambient: reference condition, no derating (ISO 8528-1).
- 45 °C ambient: about -5% output, a planning assumption to confirm with the datasheet.
- Altitude above 1000 m: about -3% output per 300 m of additional elevation, a planning assumption to confirm with the datasheet.
At 0.8 PF and 60 Hz, Philippine sites are typically 1800 rpm for a diesel set, with 440/254 V three-phase or 220/230 V single-phase output. A site that is both hot and elevated applies both derating factors together, which can push a nominally 500 kVA requirement toward a 500 kVA diesel generator or larger.
Installation: location, ventilation and sound
The generator room must bring in enough combustion and cooling air and discharge exhaust away from dock doors and air intakes. A set that runs hot or cannot breathe will not hold its rating. For sites near residential areas or with noise limits, a sound-attenuated silent diesel generator enclosure keeps typical sound levels within the dB(A) limits in the datasheet, normally in the range of 70–85 dB(A) at 1 m depending on the canopy rating. Keep the set clear of flood paths and provide service access around all four sides.
Not applicable and limitations
All figures on this page are planning values, not a quotation or a guarantee of performance. The correct set size depends on measured motor starting data, site ambient and altitude, the actual duty rating in the datasheet, and local installation rules. kVAGENSET does not state product certifications, certificate numbers, agency appointments or local stock on this page. Prices are only given as ranges or examples, never as a fixed quotation, because freight, duty and configuration change the final number. Cold-chain holding times and spoilage thresholds depend on the product and the facility and must be confirmed with the refrigeration engineer, not taken from this article.
Frequently asked questions
How big a generator do I need for a cold storage warehouse?
Size for the refrigeration running load plus motor starting. As a planning rule, multiply running kW by 1.25–1.5 and divide by 0.8 PF; an 80 kW warehouse load suggests about 150 kVA standby at 40 °C. Confirm with a load study and the motor nameplates.
Should I use standby or prime rating for cold storage?
Use standby rating where outages are short and rare, and prime or continuous where the set runs for hours as the main supply. Standby rating limits annual running hours; prime allows extended running with a 10% overload allowance for a limited period at 0.8 PF.
How much fuel does a warehouse backup generator use?
A diesel set at 0.8 PF uses roughly 0.235 L/kWh at 100% load and 0.24 L/kWh at 75% load, so a 200 kVA set burns about 37.6 L/h at full load and 28.8 L/h at 75%. Actual consumption varies with load, engine condition and ambient temperature.
How fast must the generator start to protect cold storage?
With an automatic transfer switch, power is typically restored in about 10 seconds after utility failure. The greater risk is the restart step: stage compressor starts and keep defrost heaters off for the first minutes so the first motor step does not trip an undersized set.
Spec a cold storage generator
Send us your compressor nameplates and site ambient, and we will size a standby set that holds the cold chain through the next outage.